Lead Water Service Pipe Replacement

Toronto, Ontario

completeDrinking WaterISF
Federal contribution
$18,229
Federal share21%

of $87.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
20102011
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
Sep 29, 2010(actual)
Construction end
Mar 29, 2011(actual)

Against the original forecast

  • Construction start7 months lateforecast Mar 1, 2010