Lead Water Service Pipe Replacement
Federal contribution
$18,229
Federal share21%
of $87.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
2010
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Jun 10, 2010(actual)
- Construction end
- Aug 27, 2010(actual)
Against the original forecast
- Construction start2 months lateforecast Mar 26, 2010
- Construction end4 months earlyforecast Dec 23, 2010
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36417 in the federal list. How to read these figures.