Lead Water Service Pipe Replacement
Federal contribution
$39,373
Federal share21%
of $189.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
20102011
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Oct 15, 2010(actual)
- Construction end
- Feb 4, 2011(actual)
Against the original forecast
- Construction start5 months lateforecast May 17, 2010
- Construction end8 weeks earlyforecast Mar 31, 2011
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36427 in the federal list. How to read these figures.