Lead Water Service Pipe Replacement

Toronto, Ontario

completeDrinking WaterISF
Federal contribution
$38,748
Federal share21%

of $186.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
2010
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
Aug 5, 2010(actual)
Construction end
Dec 3, 2010(actual)

Against the original forecast

  • Construction start3 months lateforecast May 17, 2010
  • Construction end4 months earlyforecast Mar 31, 2011