North York Community Basement Flooding Relief - Demaris Avenue

Toronto, Ontario

completeWastewaterISF
Federal contribution
$161,570
Federal share32%

of $500.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
20102011
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
Aug 23, 2010(actual)
Construction end
May 31, 2011(actual)

Against the original forecast

  • Construction start5 months lateforecast Mar 15, 2010
  • Construction end2 months lateforecast Mar 31, 2011