Local Road Resurfacing
Federal contribution
$18,522
Federal share27%
of $69.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
2010
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Apr 19, 2010(actual)
- Construction end
- Jun 9, 2010(actual)
Against the original forecast
- Construction end3 weeks earlyforecast Jun 30, 2010
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36454 in the federal list. How to read these figures.