North York Community Basement Flooding Relief - Fontainbleau Drive
Federal contribution
$646,278
Federal share32%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
2010
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Nov 13, 2009(actual)
- Construction end
- Aug 6, 2010(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Nov 30, 2009
- Construction end2 months lateforecast May 31, 2010
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36459 in the federal list. How to read these figures.