North York Community Basement Flooding Relief - Meadowacres Drive
Federal contribution
$290,825
Federal share32%
of $900.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
20102011
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Nov 29, 2010(actual)
- Construction end
- May 17, 2011(actual)
Against the original forecast
- Construction start9 months lateforecast Mar 15, 2010
- Construction end7 weeks lateforecast Mar 31, 2011
Also in Toronto