Subway Escalator and Elevator Overhaul

Toronto, Ontario

completePublic TransitISF
Federal contribution
$2.3M
$2,266,580
Federal share33%

of $6.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
20102011
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
Sep 11, 2009(actual)
Construction end
Oct 28, 2011(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Aug 1, 2009
  • Construction end5 weeks earlyforecast Nov 30, 2011