North York Community Basement Flooding Relief - St. Paschat Court
Federal contribution
$29,082
Federal share32%
of $90.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
20102011
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Sep 16, 2010(actual)
- Construction end
- Jan 28, 2011(actual)
Against the original forecast
- Construction start6 months lateforecast Mar 15, 2010
- Construction end2 months earlyforecast Mar 31, 2011
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36476 in the federal list. How to read these figures.