North York Community Basement Flooding Relief - Steeles Avenue East
Federal contribution
$581,650
Federal share32%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
2010
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- May 31, 2010(actual)
- Construction end
- Sep 22, 2010(actual)
Against the original forecast
- Construction start3 months lateforecast Mar 15, 2010
- Construction end6 months earlyforecast Mar 31, 2011