North York Community Basement Flooding Relief - Sunnycrest Road

Toronto, Ontario

completeWastewaterISF
Federal contribution
$145,412
Federal share32%

of $450.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
2010
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
Nov 13, 2009(actual)
Construction end
Aug 6, 2010(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Nov 30, 2009
  • Construction end2 months lateforecast May 31, 2010