Birchmount Bus Garage Repair Bay Modifications
Federal contribution
$2.4M
$2,400,333
Federal share33%
of $7.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
20102011
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Sep 11, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start6 weeks lateforecast Aug 1, 2009
- Construction end4 weeks earlyforecast Nov 30, 2011