North York Community Basement Flooding Relief - Godstone Road
Federal contribution
$1.0M
$1,034,045
Federal share32%
of $3.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
2010
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Apr 30, 2010(actual)
- Construction end
- Aug 13, 2010(actual)
Against the original forecast
- Construction start7 weeks lateforecast Mar 15, 2010
- Construction end8 months earlyforecast Mar 31, 2011
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36490 in the federal list. How to read these figures.