Bus Garage and Shops Facility Renewal Program

Toronto, Ontario

completePublic TransitISF
Federal contribution
$1.1M
$1,087,714
Federal share22%

of $4.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
2010201120122013
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
Sep 11, 2009(actual)
Construction end
Nov 30, 2012(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Oct 31, 2012