Back to projects

Toronto Police Services 14 Division - Central Lockup

Toronto, Ontario

completeAdministration, Emergency and Public WorksISF
Federal contribution
$6.6M
$6,596,881
Federal share25%

of $26.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
201020112012
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
Jun 21, 2010(actual)
Construction end
Jul 3, 2012(actual)

Against the original forecast

  • Construction start3 months earlyforecast Oct 1, 2010
  • Construction end3 weeks lateforecast Jun 14, 2012

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36543 in the federal list. How to read these figures.