Toronto Transit Commission - Facilities Roofing Rehabilitation Program
Federal contribution
$2.4M
$2,408,989
Federal share20%
of $11.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
20102011201220132014
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Sep 11, 2009(actual)
- Construction end
- Jun 30, 2014(actual)
Against the original forecast
- Construction start6 weeks lateforecast Aug 1, 2009
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36547 in the federal list. How to read these figures.