Replacement of the Victoria Park Bus Terminal
Federal contribution
$6.1M
$6,126,069
Federal share27%
of $22.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
20102011
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Sep 11, 2009(actual)
- Construction end
- May 31, 2011(actual)
Against the original forecast
- Construction start6 weeks lateforecast Aug 1, 2009
- Construction end6 months earlyforecast Nov 30, 2011
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36549 in the federal list. How to read these figures.