Toronto Transit Commission - Kipling Station Improvements

Toronto, Ontario

completePublic TransitISF
Federal contribution
$2.5M
$2,495,924
Federal share31%

of $8.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
20102011
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
Sep 11, 2009(actual)
Construction end
Sep 11, 2011(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Aug 1, 2009
  • Construction end3 months earlyforecast Nov 30, 2011