Leaside Park
Federal contribution
$63,654
Federal share32%
of $200.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
20102011
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Nov 8, 2010(actual)
- Construction end
- Dec 17, 2010(actual)
Against the original forecast
- Construction start6 weeks lateforecast Sep 27, 2010
- Construction end2 weeks earlyforecast Dec 31, 2010
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36612 in the federal list. How to read these figures.