Back to projects

Nesbitt Park

Toronto, Ontario

completeRecreationISF
Federal contribution
$29,099
Federal share29%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
2010
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
Aug 23, 2010(actual)
Construction end
Sep 17, 2010(actual)