Nesbitt Park
Federal contribution
$29,099
Federal share29%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
2010
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Aug 23, 2010(actual)
- Construction end
- Sep 17, 2010(actual)
Also in Toronto