R.V. Burgess Park
Federal contribution
$26,592
Federal share33%
of $80.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
2010
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Sep 20, 2010(actual)
- Construction end
- Nov 19, 2010(actual)
Against the original forecast
- Construction end5 weeks earlyforecast Dec 24, 2010
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36614 in the federal list. How to read these figures.