Middle Barachois Brook Bridge

St. John's, Newfoundland and Labrador

completeHighways and RoadsMIC
Federal contribution
$2.5M
$2,524,263
Federal share50%

of $5.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 30, 2010
201020112012
Built

Approved 8 months before the announcement.

Program
Building Canada Fund - Major Infrastructure Component
Construction start
Jun 10, 2010(actual)
Construction end
Jun 30, 2012(actual)

Against the original forecast

  • Construction end9 months earlyforecast Mar 29, 2013

Also in St. John's

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36645 in the federal list. How to read these figures.