Wastewater collection and treatment in Sylvie Street sector

Waterloo, Quebec

completeWastewaterCC
Federal contribution
$467,500
Federal share27%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2010201220142016
Built

Approved 6.4 years before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Township of Shefford
Construction start
Apr 1, 2010(actual)
Construction end
Dec 31, 2012(actual)

Against the original forecast

  • Construction end21 months lateforecast Mar 31, 2011