Back to projects

Reconstruction of Taylor Street

Waterloo, Quebec

completeWastewaterCC
Federal contribution
$448,717
Federal share33%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2016
Built

Approved 9 months before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Waterloo
Construction start
Sep 1, 2015(actual)
Construction end
Oct 31, 2016(actual)

Against the original forecast

  • Construction start5 months lateforecast Apr 6, 2015
  • Construction end14 months lateforecast Sep 7, 2015

Also in Waterloo

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45906 in the federal list. How to read these figures.