Revitalization of Parish of Saint-Hippolyte village core
Federal contribution
$392,448
Federal share32%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 26, 2010
2010201220142016
Built
Approved 6 months before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Municipality of Saint-Hippolyte
- Construction start
- Mar 1, 2010(actual)
- Construction end
- Feb 26, 2016(actual)
Against the original forecast
- Construction end2.2 years lateforecast Dec 31, 2013
Also in Saint-Hippolyte
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36700 in the federal list. How to read these figures.