Construction of a community center

Saint-Hippolyte, Quebec

completeRecreationSCF
Federal contribution
$575,601
Federal share33%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 20, 2017
2018
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Nov 30, 2017(actual)
Construction end
Dec 4, 2018(actual)

Against the original forecast

  • Construction start2 months lateforecast Oct 1, 2017
  • Construction end4 months lateforecast Jul 31, 2018