New main water reservoir
Federal contribution
$496,135
Federal share24%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 21, 2009
20102011201220132014
Built
Approved 6 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Mont-Joli
- Construction start
- Sep 25, 2013(actual)
- Construction end
- Jan 15, 2014(actual)
Against the original forecast
- Construction start3.3 years lateforecast Jun 15, 2010
- Construction end22 months lateforecast Mar 31, 2012
Also in Mont-Joli