Back to projects

New main water reservoir

Mont-Joli, Quebec

completeDrinking WaterCC
Federal contribution
$496,135
Federal share24%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 21, 2009
20102011201220132014
Built

Approved 6 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Mont-Joli
Construction start
Sep 25, 2013(actual)
Construction end
Jan 15, 2014(actual)

Against the original forecast

  • Construction start3.3 years lateforecast Jun 15, 2010
  • Construction end22 months lateforecast Mar 31, 2012

Also in Mont-Joli

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36708 in the federal list. How to read these figures.