Refurbishment of a multi-issue unit in 3rd North West
Federal contribution
$800,000
Federal share80%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
202220232024
Built
Approved 5 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre Intégré de santé et des services sociaux du Bas-Saint-Laurent
- Construction start
- Apr 11, 2022(actual)
- Construction end
- Apr 30, 2024(actual)
Against the original forecast
- Construction start10 months earlyforecast Feb 15, 2023
- Construction end2 months lateforecast Feb 16, 2024
Also in Mont-Joli
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58912 in the federal list. How to read these figures.