St. Laurent Municipal Road Improvements
Federal contribution
$236,260
Federal share33%
of $708.8K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 11, 2009
ApprovedOct 6, 2009
2010
Built
Approved 4 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Rural Municipality of St. Laurent
- Construction start
- Aug 16, 2010(actual)
- Construction end
- Dec 7, 2010(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jun 30, 2010
- Construction end5 weeks lateforecast Nov 1, 2010