St. Laurent Municipal Road Improvements

St. Laurent, Manitoba

completeHighways and RoadsISF
Federal contribution
$236,260
Federal share33%

of $708.8K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 11, 2009
ApprovedOct 6, 2009
2010
Built

Approved 4 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 16, 2010(actual)
Construction end
Dec 7, 2010(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jun 30, 2010
  • Construction end5 weeks lateforecast Nov 1, 2010

Also in St. Laurent

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36714 in the federal list. How to read these figures.