The St Laurent Métis Heritage Centre
Federal contribution
$80,000
Federal share33%
of $240.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 9, 2017
20182019
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Rural Municipality of St. Laurent
- Construction start
- Aug 9, 2018(actual)
- Construction end
- Sep 13, 2019(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Aug 27, 2018
- Construction end3 months lateforecast May 31, 2019
Also in St. Laurent
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51633 in the federal list. How to read these figures.