South Island Highway Improvement Project - Phase 1
Campbell River, British Columbia
Federal contribution
$4.2M
$4,222,000
Federal share32%
of $13.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 24, 2009
20102011
Built
Approved 3 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Campbell River
- Construction start
- Mar 8, 2010(actual)
- Construction end
- Jun 25, 2011(actual)
Against the original forecast
- Construction end4 months earlyforecast Oct 31, 2011