Back to projects

South Island Highway Improvement Project - Phase 2

Campbell River, British Columbia

completeHighways and RoadsSCF
Federal contribution
$3.2M
$3,215,666
Federal share33%

of $9.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 11, 2017
2018201920202021
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Campbell River
Construction start
Jun 10, 2019(actual)
Construction end
Aug 24, 2021(actual)

Against the original forecast

  • Construction start2 weeks lateforecast May 24, 2019
  • Construction end7 weeks earlyforecast Oct 15, 2021