Wastewater treatment plant and pumping station upgrades

Beauceville, Quebec

completeWastewaterCC
Federal contribution
$542,305
Federal share30%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 14, 2009
201020112012
Built

Approved 7 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Beauceville
Construction start
Oct 10, 2010(actual)
Construction end
May 31, 2012(actual)

Against the original forecast

  • Construction end14 months lateforecast Mar 31, 2011