Repair of the fire alarm system
Federal contribution
$158,433
Federal share80%
of $198.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
202220232024
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré de santé et de services sociaux de Chaudière-Appalaches
- Construction start
- Oct 4, 2022(actual)
- Construction end
- Feb 9, 2024(actual)
Against the original forecast
- Construction start4 months lateforecast Jun 1, 2022
- Construction end7 weeks earlyforecast Mar 31, 2024
Also in Beauceville
- Construction of a New Arena and Development of Various Sports Fields$3.3M
- Renovating and Upgrading of the Beauceville Pool and Cultural Centre$812.3K
- Wastewater treatment plant and pumping station upgrades$542.3K
- Upgrading the boiler room$480.0K
- Program for the renewal of drinking water and wastewater pipes$99.1K