Repair of the fire alarm system

Beauceville, Quebec

completeHealthcare InfrastructureCVRIS
Federal contribution
$158,433
Federal share80%

of $198.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
202220232024
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Oct 4, 2022(actual)
Construction end
Feb 9, 2024(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 1, 2022
  • Construction end7 weeks earlyforecast Mar 31, 2024