completePublic TransitISF
Federal contribution
$3.4M
$3,363,000
Federal share33%

of $10.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 11, 2009
ApprovedNov 12, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
Jan 1, 2010(actual)
Construction end
Oct 31, 2011(actual)