Back to projects

Sewer Pipe Replacements

Québec, Quebec

completeWastewaterISF
Federal contribution
$2.3M
$2,316,473
Federal share32%

of $7.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 13, 2009
ApprovedJan 26, 2010
2010
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Québec
Construction start
Sep 21, 2009(actual)
Construction end
Dec 4, 2010(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Sep 1, 2009
  • Construction end2 months lateforecast Sep 24, 2010

Also in Québec

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36951 in the federal list. How to read these figures.