Sewer Pipe Replacements
Federal contribution
$2.3M
$2,316,473
Federal share32%
of $7.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 13, 2009
ApprovedJan 26, 2010
2010
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Québec
- Construction start
- Sep 21, 2009(actual)
- Construction end
- Dec 4, 2010(actual)
Against the original forecast
- Construction start3 weeks lateforecast Sep 1, 2009
- Construction end2 months lateforecast Sep 24, 2010
Also in Québec
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36951 in the federal list. How to read these figures.