Childrens Hub - Toronto
Federal contribution
$1.7M
$1,684,621
Federal share31%
of $5.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 11, 2009
ApprovedNov 12, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Oct 1, 2009(actual)
- Construction end
- Mar 31, 2011(actual)