East River Road Infrastructure Renewal
Federal contribution
$612,165
Federal share33%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 23, 2009
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of New Glasgow
- Construction start
- Aug 3, 2010(actual)
- Construction end
- Dec 15, 2010(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jul 5, 2010
- Construction end2 weeks earlyforecast Dec 31, 2010
Also in New Glasgow
- New Glasgow Library and Pictou-Antigonish Regional Library (PARL) Headquarters Revitalization$3.9M
- Southend Sewer Separation (Phase II to IV)$1.5M
- New Glasgow Water Treatment Expansion$1.3M
- Water Transmission Line Replacement on East River East Side Road$1.2M
- Town of New Glasgow - Abercrombie Road Waterline Replacement$1.1M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36965 in the federal list. How to read these figures.