Development of a tourist port village in Saguenay
Federal contribution
$5.4M
$5,367,261
Federal share33%
of $16.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 2, 2009
2010201220142016
Built
Approved 3 weeks before the announcement.
- Program
- Building Canada Fund - Large Urban Centres Component
- Ultimate recipient
- City of Saguenay
- Construction start
- Aug 1, 2009(actual)
- Construction end
- Mar 1, 2016(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Sep 11, 2009
- Construction end23 months lateforecast Mar 31, 2014