Back to projects

Water pipe replacement

Saguenay, Quebec

completeDrinking WaterCWWF
Federal contribution
$4.9M
$4,912,321
Federal share50%

of $9.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 26, 2017
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Saguenay
Construction start
Jun 2, 2017(actual)
Construction end
Nov 24, 2017(actual)

Against the original forecast

  • Construction start5 weeks lateforecast May 1, 2017
  • Construction end4 months earlyforecast Mar 31, 2018