Resurfacing Route 132 in Lévis
Federal contribution
$769,295
Federal share34%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 2, 2010
Built
Approved 4 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Jul 5, 2010(actual)
- Construction end
- Jul 30, 2010(actual)
Against the original forecast
- Construction end3 months earlyforecast Oct 31, 2010
Also in Lévis
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 37218 in the federal list. How to read these figures.