Pavement Reinforcement on Route 173
Federal contribution
$789,263
Federal share39%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 3, 2010
Built
Approved 4 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Jul 5, 2010(actual)
- Construction end
- Aug 18, 2010(actual)
Against the original forecast
- Construction end2 months earlyforecast Oct 31, 2010
Also in Saint-Henri
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 37223 in the federal list. How to read these figures.