Replacement of the refrigeration system of the municipal arena
Federal contribution
$340,121
Federal share33%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 25, 2017
2018201920202021
Built
Approved 6 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of Saint-Henri
- Construction start
- May 17, 2017(actual)
- Construction end
- Nov 24, 2020(actual)
Against the original forecast
- Construction start5 weeks lateforecast Apr 15, 2017
- Construction end3 years lateforecast Nov 30, 2017
Also in Saint-Henri
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49961 in the federal list. How to read these figures.