Back to projects

Repairs to Highway 20 West in Saint-Vallier

Saint-Vallier, Quebec

completeHighways and RoadsISF
Federal contribution
$1.5M
$1,457,500
Federal share50%

of $2.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 3, 2010
Built

Approved 4 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Jul 6, 2010(actual)
Construction end
Nov 26, 2010(actual)

Against the original forecast

  • Construction end3 weeks earlyforecast Dec 15, 2010

Also in Saint-Vallier