Federal contribution
$3,535
Federal share46%
of $7.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2016
2016
Built
Approved 13 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Club Motoneige Bellechasse
- Construction start
- Sep 21, 2015(actual)
- Construction end
- Dec 7, 2015(actual)
Also in Saint-Vallier