Bridge Replacement on Halfmoon-Carlson Forest Service Road
Federal contribution
$62,400
Federal share48%
of $129.8K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedApr 7, 2009
ApprovedOct 29, 2009
20102011
Built
Approved 7 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Aug 16, 2010(actual)
- Construction end
- Feb 18, 2011(actual)
Also in Sechelt
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 37279 in the federal list. How to read these figures.