Upgrades to North-Baezaeko Forest Service Road

Nazko, British Columbia

completeHighways and RoadsISF
Federal contribution
$165,000
Federal share47%

of $350.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedApr 7, 2009
ApprovedOct 29, 2009
2010
Built

Approved 7 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jun 9, 2010(actual)
Construction end
Nov 1, 2010(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Jul 1, 2010
  • Construction end4 weeks earlyforecast Nov 30, 2010

Also in Nazko

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 37281 in the federal list. How to read these figures.