Michelle-Coglistiko Forest Service Road Upgrade
Federal contribution
$230,000
Federal share46%
of $500.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 1, 2010
Built
Approved 5 weeks before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Jun 17, 2010(actual)
- Construction end
- Oct 31, 2010(actual)
Against the original forecast
- Construction end5 months earlyforecast Mar 31, 2011
Also in Nazko
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40244 in the federal list. How to read these figures.