Upgrading the Granisle Cutoff Forest Service Road

Granisle, British Columbia

completeHighways and RoadsISF
Federal contribution
$230,000
Federal share50%

of $460.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedApr 7, 2009
ApprovedOct 29, 2009
2010
Built

Approved 7 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 17, 2010(actual)
Construction end
Dec 6, 2010(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jul 31, 2010
  • Construction end4 months earlyforecast Mar 31, 2011

Also in Granisle

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 37287 in the federal list. How to read these figures.